Nigeria electricity crisis no likely go resolve for 2026, as di goment don shift di settlement of im N3.3 trillion debt to power generation companies to 2027, while major interventions for metering and transmission infrastructure also expected to extend beyond this year.
Di Minister of Power, Joseph Tegbe, disclose dis one during interview with Arise News yesterday, adding say di government don pay N1.23 trillion of di debt, wey dem negotiate down from initial N6 trillion, and dey explore options to clear di outstanding balance.
Dis one include offsetting obligations against royalties and corporate income tax, as well as engaging di Nigerian National Petroleum Company Limited, NNPC, to reduce gas costs for power generation companies.
"We dey on track to finish paying di rest next year. Because we dey look at different ways to settle am," Tegbe talk.
On di proposed debt offsets, he talk say: "You no fit take money with one hand and give am with di other hand. So, make we net am off."
Tegbe attribute 80 per cent of di sector challenges to human and institutional factors, with technical issues accounting for di remaining 20 per cent.
"I talk say di problem for power sector na 20 per cent technical, 80 per cent human," he talk, dey identify poor teamwork, lack of coordination among operators, liquidity constraints and governance issues as major obstacles to efficiency.
He also criticise past investment decisions, dey talk say some projects na political considerations drive rather than proper planning.
"From technical point of view, I go tell you di biggest issue: na say we don dey throw money at wrong things," he talk.
Di minister talk say im ministry dey review ongoing projects to prioritise investments wey fit improve electricity access.
Tegbe recently project say stable electricity supply fit take another three to five years. He also announce plans for $2 billion East-West Super Grid project to expand transmission capacity from about 4,000MW to 19,000MW.